#ElectrificationEntry# 3128126
/blog/post/3128126Entry# 3436818
/blog/post/3436818
-----
Delhi - Rewari - Jaipur Electrification:
Jul 2018 Status
-----
GGN Gurugram - BWSN Bijwasan
--
No wiring work at Palam Vihar, Allawardi Fatak
But Wiring work in progress between Allawardi to Bijwasan
About 60% wiring finished
Labourers found all along in various posts in one line block and other track is open where trains ran as usual...
Fixing Crossbeams Finished in Elec Portals at BWSN Bijwasan Rly Stn...
-----
GGN Gurugram - BWSN Bijwasan
--
Elec foundation works finished
Elec Poles are FIXED to foundation 90%
Elec Portals are FIXED to foundation 90%
Crossbeams for Elec Portals FIXED 90%
Elec Poles/ Portals where cantilever assembly FIXED 90%
Wiring completed 60%
-----
BWSN Bijwasan Rly Stn
--
Elec foundation works finished
Elec Poles are FIXED to foundation 90%
Elec Portals are FIXED to foundation 90%
Crossbeams for Elec Portals FIXED 80%
Elec Poles/ Portals where cantilever assembly FIXED 40%
Wiring completed 0%
-----
---------------------
rojaRAJU, O+
===========