Delhi - Rewari - Jaipur Electrification:
Jun 2018 Status
-----
Traction Sub Station (TSS) at GHH Garhi Harsaru Junction
--
Foundation works for towers, bays finished
Towers erection finished
Transformers fixed
Isolation, Switchgear, other equipments fixed
Pending works:
- Feeder Input from State Power Distribution Board
- Cabling within Sub Station
- Output to Traction Masts
- Walkways to bays/ Platforms Civil works
- Commissioning of TSS
-----
---------------------