Mmts phase 2 works on maulali c cabin ghatkesar on full speed.3 rd line laying 95% complete 4 th line 80 % complete electrification 70% signalling works also complete.track linking work at maulali and ghatkesar with main line not started.station building and s&t buildings complete at maulali cherlapally