Updates on ET-JBP electrification as on 6/2/2017.
1. The work of ET-PPI is approximately 99% completed.the bagratawa bridge and tunnel is now fully under wires.i think by this pace of work at the end of this month we can see the elocos on ET-PPI section.
2. The work of electrification is started on NU-PPI section.the pole work is done til kareli and work of pole is going on kareli station.the work of hole is completed till gadarwara and work of digging hole is in progress from GAR-PPI.
1,2...
more... & 3pics are of Sontalai station which is completed under wires.
4 pic is of sub-station on bagra tawa station whose work is in progress.
5 & 6 pic is of bagra tawa station which is fully under wires now.
7,8,9,10 & 11 are the pics of Pipariya Station whose work of electrification is fully done.
12 pic is of karakbel station.
13 & 14 pic is of sridham station.
15 is of near bhetaghat station.
16 pic is of narsinghpur station whose only wiring work is left.
By this pace of work i think we can see the elocos on full ET-JBP section at the end of June 2017.