Yes... Work is is going on... But on slow pace...
Find my observations during my travel from kWV to Bhigwan....
Update on Kwv- Bhigwan Doubling,
From Kurduwadi to dhavlas No visible work is seen along the track...
Few...
more... km before Kem station .. some ground leveling work is seen...
Some station work and bridge work seen near bhalawani station... Also leveling work seen till Jeur railway over bridge...
No station work seen at Kurduwadi, Jeur, Dhavlas, Kem, stations....
From Jeur to pophalaj intermittent ground leveling is seen along the track...
From pophalaj no work done along the track...
After Pophalaj no work is seen...till bridge on ujni backwater...
Old bridge have facility for second track so no new bridge may be required...
In nearby washimbe area stone cutting and ground leveling is seen nearby Washimbe station on right side...
Till parewadi station intermittent ground leveling and stone cutting seen along track...
After Parewadi ground leveling is seen till Bhigwan...
SUMMERY:
1. Ground leveling and stone cutting going on.
2. Station work for new tracks, platforms, loop lines not seen.
3. All 4 bridges (3 on Ujni backwater and 1 on Bhima river) are seen having spare area to accommodate extra track, steel girders seen at all bridges.