2007
• Land acquisition activities started - 10th Aug, 2007
• Land lease deed signed with Uttar Pradesh Govt - 16th Jan, 2009
• Inauguration of construction of factory boundary wall by the Hon’ble Chairperson, UPA
Smt. Sonia Gandhi - 27th Jan, 2009
• Completion of Factory Boundary Wall - Dec, 2010
• Completion of Rail Connectivity - Jan, 2011
• Commissioning of 33 KV Transmission line & substation - Jan, 2011
• Roads for Phase I - Started - Oct 2010, Completed - Mar, 2011.
• Finishing Shop - Started - Sept 2010, Completed - Feb, 2011.
• Furnishing Shop - Started - Sept 2010, Completed - Apr, 2011
• Phase-I Production (First coach ready) - 8" April, 2011
Milestones of the Rail Coach Factory
• Dedication of the Factory to the Nation - 07 Nov, 2012
• Nos of Coaches out in Year 2011-12 - 18
• Nos of Coaches out in Year 2012-13 - 70
• Nos of Coaches out in Year 2013-14 - 130
• Nos of Coaches out in Year 2014-15 - 140
Source of this Info:
click hereProject Schedule
DESCRIPTION TARGET DATE OF COMPLETION STATUS
Construction of Phase-I work: Furnishing and Finishing group of shops, temporary office and storage space, temporary accommodation and logistics support including specified M&P, T&P and embedded track, supporting electrical installation. March’ 11 Work Completed
Construction of Phase-II & III work: Shell assembly Shop, Bogie Shop, Wheel Shop, Paint Shop, Machine Shop with full M&P, T&P and Stores with logistic Support. Administrative building, Technical Training Center, Hostel, Township - Housing, Service buildings, Shoping complex & Sports complex etc. Dec’ 14 Work in Progress
Source of this Info:
click hereLook till now the Crucial Phases of the Project i.e Phase II & III are under progress in RCF Raebareli how pathetic where demand for LHB Coaches are mammoth in IR.
Both Screenshots are attached for ready reference.
Screenshot of Map of RCF Raebareli is also attached.
Link of Map:
click here In 5 Years 358 Coaches made by this factory.
Average Production per year: 71 Coaches (Very Poor & Frustrating Progress)