Sep 24 2021 (15:53) By Currently march 50 2022, approx done , 100km more will be done commissioned out by of march 250 2022 km So total 150 km will be done out of 250 km But No work started between beohari to Sareigram (100 km) due to forest dept claims and sanjay national park Apart from that remaining work is going in good pace
Currently 50 km approx done , 100km more will be commissioned by march 2022. So total 150 km will be done out of 250 km. But No work started between beohari to Sareigram (100 km) due to forest dept. claims and sanjay national park. Apart from that remaining work is going in good pace .
Important Note:This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks. Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.