#JodhpurDeganaPhulera updates for October
Total cost about 1600 cr
Physical progress 22% & 27%
Till now crore
Expenditure 8.6 + 3.27 crore
Earthwork...
more... 32,000
Remaining earthwork 11.7 lakh cum
Minor bridges completed 9
Remaining minor bridge 93
Major bridges
Ballast 11,000 cum + 11,000 cum
Remaining Ballast 5 lakh 21 thousand cum
Blanketing 10,000 cum + 11,000 cum
Remaining Blanketing 3 lakh cum
.
Waiting for track linking to start