Railway board has approved for Pre NI and NI working for construction of 3rd line with Electrification Laying and Linking of track between BGSF-JMKT-OPL
in KZJ-BPQ Section with following instructions: Duration of block work: a. Pre NI working for 10 days (Monday to Wednesday) 27.06.2022 to 06.07.2022
b....
more... NI working for 14 days (Thursday to Wednesday) 07.07.2022 to 20.07.2022
Train no.12649/12650 was diverted in between KACHEGUDA and MAJRI from 26th June 2022 to 19th July 2022.
Diverted to MAJRI - PIMAL KHUTI - MUDHKED - NIZAMABAD, stoppages eliminated:- Balharshah.