The time line for completion of #Electrification of entire BG routes of IR is as under:
.
Year Target (Route Kilometre)
2019-20 6,000 (2454 route kms achieved upto 01.01.2020)
2020-21 6,000
2021-22 6,000...
more...
2022-23 6,500
2023-24(upto Dec-23) 4,310
Total 28,810
.
This information was given by the Minister of Railways and Commerce & Industry, Shri Piyush Goyal in a written reply to a question in Lok Sabha today.