at Chitrasani
6-7. Direct layed track on transit with an Alco moving towards Palanpur side
8. Abu Road Pf#1
9. Bridge construction at Abu Road outer
10. Luniyapura Bridge no. 793 (ABR) outer under construction
11. Track layed between ABR outer bridge and Morthala outer bridge
12. GL near Morthala
13-14 minor bridge construction
15-17 intermediate track layed ,
GL going on , JCB doing its Job
18-24. Major Bridge construction at Morthala outer (full height)
25. immediately After bridge ends, GL in progress till morthala station
26-30. Morthala bridge construction (towards ABR)
31-33. Second track layed from Bhimana stsn to Morthala side partially .
34. Ajmer Ahmedabad Intercity change its track from double line to single line at Bhimana outer .
*тЧ╜ Wiring done till Amirgadh (excl. first loop and Palanpur stsn)
*тЧ╜Post Bhimana WDFC GL going on at high pace near Swarupganj, Banas station
*тЧ╜ prime focus of WDFC is from Rani to Sojat Road intermediate location double Track laying done at some place 1st track layed ,and work in progress for 2nd track .
1 or 2 bridge have been constructed and stone arrangement can be seen there.
*тЧ╜ As per the target ,they want to commission WDFC 's (Rani - Sojat Rd.) Asap.
*тЧ╜ after this patch the coming target is of Sojat Haripur , this stretch is also in its advanced stage , very soon track laying can be seen .
#AhmedabadDelhiElectrification#AhmedabadAjmerDoubling