In the Project- Ratlam Mhow Khandwa Akola GC.
In WR Section, only 5th part - Mhow Sanawad GC is pending.
WR should now divide it into below 2 more sections:
1) Mhow to MKT/Mukhtiara Balwada ( where is, Forest land clearance is pending at 2nd final stage)
And...
more...
2) MKT/Mukhtiara Balwada to Sanawad. (No forest land required. Existing MG land will be use for BG, only Narmada river bridge needs to repair).
.....
So
MKT/Mukhtiara Balwada to Sanawad GC project can be start, without any issue.
Why WR and Ratlam Division officer don't think like this way???
Please share your inputs.